In England the requirement is set by the Building Regulations and explained by the Approved Documents, with building control deciding on the project in front of it. This page, and the three that follow it, cover England only — not the rest of the United Kingdom.

On this page

Review guidance, not legal advice. Whether a project complies, and how it demonstrates that, is for the designer and the building control body — not for a drawing review.

The system

How England's system is built

Three layers: the regulation, the guidance on meeting it, and the body that decides on the project.

Instruments in England
Building RegulationsRegulation. Sets the requirements — schedule 1 lists them by part, including access, ventilation, stairs and guarding
Approved DocumentsStatutory guidance. Explain one practical way of meeting a requirement; other routes to compliance may exist
Building control bodyThe local authority or a registered approved inspector. Decides whether the work meets the regulations
Dutyholder dutiesDuties that sit with the client, the designers and the contractors on a project, including where a principal designer is appointed
Project specificationContractual, not statutory. Frequently stricter than the regulations, and binding because it is agreed
Published standardsTechnical documents referenced by designs, specifications or guidance — including British Standards
An Approved Document is the common route, not the only route. An alternative design that meets the requirement is still a valid answer if the building control body accepts it.

Responsibility

Who is responsible for what

A drawing review informs people; it does not take over anyone's duty. Knowing who owns each answer is what makes a review usable.

  1. The designer who drew it

    Owns the design, the dimensions and the specification, and answers the questions a review raises.

  2. The client or dutyholder

    Owns the brief, the procurement route and the decisions that change scope — including anything the brief requires beyond the regulations.

  3. The principal designer, where one is appointed

    Coordinates the design work and the information that goes with it on projects where such an appointment is required.

  4. The contractor

    Builds to the documents, raises queries where the documents conflict, and is responsible for the work as executed.

  5. The building control body

    Decides whether the work meets the regulations, and can accept a route to compliance that is not the common one.

Scope

England is not the United Kingdom

Building regulation is devolved. ROMURE treats each nation separately, and does not apply England's guidance to a project in Scotland, Wales or Northern Ireland.

England

  • The Building Regulations and the Approved Documents
  • Building control through a local authority or a registered approved inspector
  • This page and the three documents linked above apply here

Scotland, Wales and Northern Ireland

  • Each has its own building regulations and its own guidance documents
  • Scotland's system has its own technical guidance and verifiers
  • Wales has its own published guidance editions
  • Northern Ireland has its own regulations and technical guidance
  • ROMURE's pages for these nations are planned, not published — and are never presented as covered

Coverage

ROMURE's England coverage

Partial England coverage — Approved Documents M, K and F

ROMURE applies Approved Document M1 (dwellings), M2 (non-dwellings), K and F1 (dwellings) to England projects, as active verified packs with their editions and clauses recorded. The coverage is partial: each pack covers the scopes it was encoded for and nothing else, and England is not the United Kingdom — Scotland, Wales and Northern Ireland have their own building regulations, no rule is registered for them, and England's approved documents are never applied to a project there.

Approved Document F1 is two editions in the registry. The 2021 edition is the one in force today and the one a review applies. The 2026 edition is published but not in force before 24 March 2027, so it is carried as recorded-not-active and no review applies it in the meantime.

Drawing-based review — geometry, dimension, clearance, coordination and schedule checks — runs regardless, and each finding states its basis. See the service review and the coverage table.

Start with one sheet

England project, drawings in front of you?